Represented Lithuanian company in ICC construction arbitration and Swedish arbitral award annulment proceedings

Our arbitration team successfully represented a Lithuanian company that acquired a EUR 4 million claim against global conglomerate GE Power (former Alstom Sweden).

In 2016–2018 Motieka & Audzevicius successfully represented the Lithuanian client in its case against GE Power (former) Alstom in ICC arbitration in Stockholm, where the tribunal awarded the client EUR 2,6 million.

GE Power then filed for an annulment of the ICC award before the Svea Court of Appeal, where our arbitration team has again successfully represented the client.

The annulment application was based on grounds related to corruption allegations and verdicts adopted in UK criminal proceedings. In April 2021, we have successfully convinced the Svea Court of Appeal to reject GE Power’s annulment application. After examining GE Power’s appeal, in March 2022, the Swedish Supreme Court decided not to grant leave for GE Power’s appeal and allowed enforcement of the ICC award against GE Power.

Our team has represented the client throughout the ICC arbitration proceedings and Swedish annulment proceedings. This case is significant as to date there were no developed practice regarding corruption allegations in Swedish courts.

Message was sent successfully

Send a message

    Submit
    Business law firm in Lithuania - Motieka
    Cookie Settings

    We use cookies to improve your experience and the performance of our site, to provide social media features and to analyse our traffic.

    Cookies are small textual files containing identifier that are sent by a web server to your web browser and are stored by the browser. The identifier is then sent back to the server each time the browser requests a page from the server.

    Cookies do not typically contain any information that personally identifies a user, but personal information that we store about you may be linked to the information stored in and obtained from cookies.